English
Market Sector Emergency Field Hospitals

Joseph Brant Hospital

29
Apr

Client

  • Joseph Brant Hospital, Burlington, Ontario – Emergency Response Facility

Challenge

  • To meet the COVID-19 crisis the hospital needed to add more beds immediately.

Solution

  • 50′ wide by 165′ long Sprung Structure.

Time-line:

  • Delivery and Construction 14 days

Results

  • Sprung Structures and BLT Construction teamed up to supply and construct a temporary Pandemic Response Unit to expand the hospital’s bed capacity in preparation for the anticipated surge of COVID-19 patients. This modular structure was built on the hospital grounds and connected to the South Tower. It will provide 93 additional beds for patients who require hospitalization and treatment for COVID-19. The construction of the Pandemic Response Unit will allow the hospital to preserve our critical care and high acuity patient beds for our sickest patients. Physicians from the Burlington community are volunteering to provide patient care in the Pandemic Response Unit, treating COVID-19 positive patients with acute care needs who may require oxygen therapy and ongoing monitoring.

Delivery and Construcition in 14 Days

Saturday March 28, 2020
Sunday and Monday, March 29, 30, 2020
Tuesday March 31, 2020
Wednesday April 1, 2020
Thursday April 2, 2020
Friday April 3, 2020
Monday April 6, 2020
Thursday April 9, 2020
Saturday April 11, 2020

Call